ERCOT spent this week doing two things at once that do not obviously fit together. On Tuesday it told everyone the grid will sail through a record summer. On Monday and Tuesday its board voted to ration access to that same grid, because the queue of people who want on it has reached a number that is not real. The summer peak it is planning for is 92,211 MW. The data center load that asked to interconnect in the first few months of this year is 438,000 MW. One of those numbers is a forecast. The other is a fantasy with a cover letter.
That gap — between what Texas can deliver and what Texas has been asked to deliver — is the whole story right now, and this week it turned into a question about authority. Who gets to say yes. Who gets to say no. ERCOT is building itself a triage desk. Hyperscalers are routing around the desk entirely by bringing their own generation. And the communities at the bottom of the stack are discovering, in El Paso and in Hood County, exactly how little "no" they actually own.
92,211 MW, and ERCOT Is Calling Its Shot
Start with the number ERCOT actually stands behind. In its summer outlook released June 3, the grid operator forecast an all-time peak of 92,211 MW, nearly 10% above last summer's 83,679 MW and about 8% above the standing record of 85,464 MW set in 2023. And then it did something it has not done comfortably in years: it said the grid will hold. ERCOT puts the probability of a grid emergency at 0.09% in June and 0.21% in July, on the strength of roughly 11 GW of new capacity — overwhelmingly solar and batteries — added in the last few months.
The composition of the record is the part worth sitting with. This is not an air-conditioning peak inching up with the heat index. ERCOT attributes the growth to industrial load — crypto mining, oil and gas electrification, LNG export terminals, and data centers. The Texas peak has stopped being a weather event and become a balance-sheet event. That is good news for anyone selling firm capacity into ERCOT and a structural problem for anyone who assumed the demand curve would behave like it did in 2015.
438 GW Walked In. ERCOT Built a Door.
Here is the number nobody stands behind. In the first few months of 2026, nearly 200 data centers and large users asked to connect to the Texas grid, seeking a combined 438 GW — more than five times the entire state's record demand. ERCOT will tell you plainly that most of it will never be built. The problem is that under the old individual-study model, the speculative requests and the real ones moved through the same pipe at the same speed, and the pipe stopped working.
So on June 2 the board voted to approve the framework that allocates transmission capacity only to large loads that are, in ERCOT's words, "studied and committed" — a batch-study process that screens for the unglamorous evidence a project is real: site control, financing, an actual customer. The framework now goes to the PUCT for final sign-off. Strip away the procedure and the meaning is blunt: ERCOT has appointed itself the body that decides which AI ambitions get to count. When the queue is five times the grid, gatekeeping is not bureaucracy. It is the product.
Air-Cooled and Half Off-Grid: Google Builds Its Own Yes
If the queue is the bottleneck, the obvious move is to skip the queue. On June 4, Google and Intersect Power broke ground on the Meitner Energy Center in Gray and Roberts Counties, a Panhandle data center co-located with more than 1 GW of wind, solar, storage, and on-site gas for firming. It is the first project since Google closed its roughly $4.75 billion acquisition of Intersect in March, and the second Google-Intersect co-location in Texas after the Haskell County solar-and-storage build.
The design reads like a checklist of every objection Texas data centers have collected over the past year. It is air-cooled — restroom-level water use, in a region where water is the fight. It comes with an 800-acre workforce hub for up to 3,500 construction workers and a $10 million Texas Water Impact Fund. Google is not just building the power next to the load to dodge the interconnection queue. It is pre-buying the social license to dodge the second queue — the one made of neighbors. Build your own generation, build your own goodwill, and you never have to ask ERCOT or the county for permission you might not get.
El Paso Tries to Take a Yes Back
Which brings us to the neighbors, who are done asking nicely. On June 2, El Paso District 2 representative Josh Acevedo put an item on the June 9 council agenda to terminate the Chapter 380 incentive agreement with Meta for its $10 billion data center in Northeast El Paso. The facility broke ground last October and is designed to run behind-the-meter on 366 MW from 813 modular gas generators — roughly $473 million of equipment — for a five-year bridge period before any grid connection.
The city pushed back within 24 hours, warning that tearing up an executed agreement has no clear legal basis and could expose taxpayers to more than $1 billion in liability. This is a different animal than the zoning fights and one-year moratoriums we have covered before. Those were communities trying not to say yes. El Paso already said yes, in writing, and is now trying to find the unsay button. The behind-the-meter gas — 813 engines running off-grid in a city with air-quality problems — is what turned an incentive deal into a recall campaign. The vote is June 9.
Hood County Has No Off-Switch to Reach For
El Paso at least has a contract to fight over. Hood County has almost nothing. The Texas Tribune this week mapped eight proposed data centers across more than 7,600 acres — roughly 12 square miles — of the rural county southwest of Fort Worth. The flagship Comanche Circle development and its two siblings could draw up to 3 GW at full build, enough for about three million homes, and would need a 95-million-gallon initial fill plus 150,000 gallons a day after that. Hood County now ranks sixth among Texas counties by planned data centers.
The commissioners court rejected a development pause, and here is the thing: even if it had wanted to stop the projects, it largely cannot. Texas gives unincorporated counties almost no zoning authority. This is not an oversight developers are exploiting by accident — it is the entire reason rural, unincorporated land is the preferred address. Google picked unincorporated Panhandle counties for Meitner for the same structural reason. The places with the least power to say no are, predictably, the places being asked the loudest. That is not a coincidence. That is the siting strategy.
What to Watch Next Week
El Paso council, June 9. Acevedo's motion to kill the Meta agreement either dies in committee, gets tabled, or forces the city to litigate its own incentive deal against that $1 billion liability warning. Whatever happens, it sets the template for every Texas city that wrote a Chapter 380 check it now regrets.
The PUCT's move on Batch Zero. The board approved the framework; the Commission has to finalize it. Watch for the feasibility criteria — exactly how much site control and financing a project must show to keep its place — and how fast the 438 GW gets winnowed once the screen is live.
SB6 final rule. The large-load interconnection rule under Project 58481 is on track for adoption by mid-year, including the 75 MW threshold and the $50,000-per-MW non-refundable fee. That fee is the cheapest, bluntest filter ERCOT has — watch how much of the speculative queue simply declines to pay it.
The first real heat. June and July will test the 92,211 MW forecast against actual load, and the roughly 15 GW of installed batteries against the moment they were built for. ERCOT called its shot in public. The thermometer gets a vote.
County zoning authority. Hood County's powerlessness is becoming a legislative talking point. Watch for noise about giving counties large-load review authority ahead of the 2027 session — the single change that would most alter where these projects get built.
Disclaimer: The Grid Report is Barrio Energy's market intelligence product. Nothing here is investment advice, and Andi is not your broker. Links go to primary sources wherever possible; form your own view.



